Construction Update 3rd Week of July

Construction Update 3rd Week of July

Construction Update 3rd Week of July Update the construction results of the Prime Pano project- Pile drilling for the show unit is 90% complete.- Start work to adjust the ground and make temporary roads within the project. Work with us Suggestion Make an appoinment to...
Construction Update 2nd Week of July

Construction Update 2nd Week of July

Construction Update 2nd Week of July Update the construction results of the Prime Pano project- Pile drilling for the show unit is 45% complete.- Start work to adjust the ground and make temporary roads within the project. Work with us Suggestion Make an appoinment to...
Construction results for the 1st week of July

Construction results for the 1st week of July

Construction results for the 1st week of July Update the construction work of Prime Pano project. Pile drilling ceremony for Prime Pano model house. To begin construction. Work with us Suggestion Make an appoinment to visit the project Follow good stories with Phuket...
Summary of work for the 2nd week of March

Summary of work for the 2nd week of March

Summary of work for the 2nd week of March Update the construction work of the Prime Pano project. The soil survey has been completed. Continue to adjust the area to plan various systems within the project, such as retention ponds, drainage channels, roads, etc....
Summary of work for the 1st week of March

Summary of work for the 1st week of March

Summary of work for the 1st week of March Construction update work of the Prime Pano project. Adjust the area and roads of the Prime Pano project and conduct a soil survey to know the type of soil, the arrangement of the soil layer, and the groundwater level for...